Login  |  Register          Subscribe to Modern Materials Handling and MHPN
Zibb
Subscribe to Modern Materials Handling and MHPN
Email
Print
Reprint
Learn RSS

New roots

Extensive customization of farm tractors requires maximum handling flexibility at Case New Holland's right-sized plant.

By David Maloney, Senior Editor -- Modern Materials Handling, 10/1/2003

Just as the tractors made by Case New Holland Inc. (CNH) have made the American farmer more productive, CNH needed to find some new manufacturing efficiencies of its own.

To begin, CNH integrated its manufacturing operations in Racine, Wisc., as it right-sized for a leaner market for farm tractors. CNH closed a 1.5 million square foot assembly building in Racine and moved those operations into a nearby 600,000 square foot facility that had built transmissions. The transmissions facility was expanded by 60,000 square feet with the addition of new docks, a paint system and a testing area. At the same time, CNH took a close look at its materials handling practices and equipment.

Continuously moving conveyor lines replaced the indexing lines of old. Specially-designed carts (Topper Industrial) transport transmissions and chassis between assembly stations. A new cab delivery system uses a monorail to deliver cabs just as they are needed to the assembly line. More familiar materials handling equipment, such as a power-and-free conveyor for the paint shop and in-floor tow-line conveyors, were brought in too, striking the right balance between flexibility and productivity.

What gets done in the new facility is different too. Cab and chassis assembly lines were introduced to the facility, where before only transmissions, axles and other key components had been produced. Some of the machining, paint and subassembly work that had also been previously done there is now outsourced to suppliers.

Although the plant now builds eight models of tractors under the Case and New Holland brands, the range of options available requires considerable differentiation tractor to tractor. That put a heavy emphasis on flexibility.

'With our dual-brand strategy, we have numerous components that differentiate them,' says Jason Martin, materials team leader. 'There is also a lot of optional content. Around 95% of product is unique by the time it comes off the line.'

Production is build-to-order within the facility, with transmissions manufactured first. These are built on carts moved along on in-floor rails. The carts are designed to handle the options available for each model with supports that flip up or down depending on the requirements. Steps are integrated into the carts to allow shorter workers to reach their assembly tasks more easily. Built-in fork channels additionally permit lift trucks to return emptied carts to the beginning of the assembly process. A few articulated trucks maneuver in the tight confines of the facility.

The cart is then pushed onto an in-floor tow conveyor for assembly of the chassis, which combines the transmissions, axles and engines. It is also the point where another clever cart solution is employed to resolve a problem that occurs during the addition of the front axle. When the axle is placed on the assembly, it changes the center of gravity, and the original transmission cart can no longer hold the load without tipping. One option was to transfer the load to another cart, but that would require additional handling steps. The solution chosen was to simply add a small connecting cart to the front of the load to support the front axle. This cart just rides along on the tow conveyor with the rest of the chassis line.

Another big adjustment was moving from the indexing conveyor line that paused at work stations in the old building to a continuously moving line.

'Joining large 3,500–4,000 pound pieces of iron while moving is challenging,' Martin adds, as workers had to learn to assemble while their work rolled along.

Once assembly on this line is complete, the chassis are lifted off their carriers with a new power-and-free conveyor and taken through a wash, paint and curing process.

The cab assembly line features several materials handling highlights too. The conveyor system uses non-powered rollers that accommodate the racks holding the cabs. The rollers, each about a foot wide, are set in two rows spaced about three feet apart, similar to railroad tracks. Workers simply push the carts on the rollers as work progresses. Sections of this conveyor line are designed to raise, lower and tilt to present the work to operators at a more ergonomic position.

The sophisticated cab delivery system was also new to the Racine facility. A monorail retrieves the cab from its cart and carries it overhead to a buffer area where about half a dozen cabs are held until ready to meet the chassis in the main assembly line. Buffering overhead frees up floor space. The two lines are then synchronized together so that the cab can be dropped in perfect position down onto the chassis.

'The systems have done what we wanted,' says Martin. 'Within just a couple days of start-up we had the first product roll off the line on schedule. Overall, the facility has been a great success and is helping us to strengthen our leadership position in agricultural tractors.'

 


Click on the icon to read how John Deere builds tractors at its award-winning facility in Augusta, GA.

 

 

Case New Holland
Racine, Wisconsin

Products manufactured: Farm tractors

Facility size: 620,000 square feet

Upgrade completed: 2002 (originally built in 1967)

Employees: 500 plus

Daily output: 25 tractors

Typical SKUs per tractor: 2,500

Operations: one shift, 5 days a week

 

RECEIVING

Components for the machine shop arrive at nearby docks (1) and are transported by lift trucks to the various machine shop cells (2) where work will be performed to create valves, clutches, axles and other parts. Some of these parts are used for assembly in Racine, while others ship to plants elsewhere.

Engines, frames, large castings and gearboxes are received at docks (3) near transmission assembly (4) . Lift trucks take these parts to line-side positions.

Cabs and other parts for main assembly enter at docks on the opposite side of the building(5).


TRANSMISSION ASSEMBLY

Transmissions are built-to-order on rolling carts that carry them through the transmission assembly area (4) . Housings, drives, speed and range components are joined as the units progress along on rails embedded in the floor. Power pushers assist in moving the heavy transmissions between stations. Embedded turntables are located at various points to redirect the assembly line to better utilize the footprint of the building. Overhead cranes and manipulators assist in moving heavy parts into place.

After major components are assembled, the transmissions come to the end of the rail line where an in-floor tow conveyor catches the cart and passes it through stations where hoses and pumps are added to the assembly.

Once complete, the transmissions next go to a test and staging area (6) . CNH buffers some 50 transmissions of various types (about two days worth of production) to assure that main tractor assembly will never be delayed for lack of a transmission. The transmissions remain on their assembly carts, staged in rows on in-floor rails. Turntables allow access to any of the transmissions, so that sequence can be easily altered.


CHASSIS ASSEMBLY

Assembly of the chassis does not begin until its accompanying transmission is complete. The transmissions are rolled from the buffer area and to a tow-line conveyor that carries them through chassis assembly (7). The engines are built elsewhere as part of a joint venture between CNH and Cummins. They are shipped to the facility and brought by lift trucks from the docks (3) to chassis assembly where they are dropped onto large roller conveyors. A back-up of each type of engine is also stored in racks at receiving to assure that work can proceed at all times.

The engines and axles are added using overhead cranes. When the chassis is complete, the load is transferred to a power-and-free conveyor for transport through washing, painting and a curing process (8) . Once finished, the power-and-free drops the chassis, now weighing between 15,000-19,000 pounds onto another cart designed to carry a range of chassis models.


CAB AND TRACTOR ASSEMBLY

Cabs arrive from the supplier in racks and are placed on in-floor roller conveyors for transport through the cab assembly line (9) . The non-powered rollers in the conveyors, each about a foot wide, are aligned parallel to each other and are approximately three feet apart, similar to railroad tracks. Workers simply push the cabs along, adding components to the assembly. The system is designed so that at certain points, a conveyor section can tilt up to allow work under the cab, or a section can raise and lower to keep work at an ideal ergonomic height.

Assist devices are used to add seats, hoods and fenders, while robots seal the glass windshields. Once all work is completed, an overhead monorail lifts the cab assembly from its rack and carries it to the main tractor assembly line (10) . Half a dozen cabs can be accumulated on the monorail at once. When ready, a cab is positioned over a chassis moving down the main line on a tow conveyor. The two lines are synced together as the cab drops onto the chassis.

Final components are then added. Tires are mounted using finger-tip-controlled manipulators. Empty carts that carried the chassis before tire mounting are gathered by lift truck and taken back to the beginning of the line. Once assembly is completed, the tractor is driven to a testing and minor repair area (11) and then out through a shipping door (5) .

 

 

System Suppliers

Carts & carriers: Topper Industrial, 800-529-0909, www.topperindustrial.com

Systems consultants: Mid-States Engineering & Manufacturing, 800-346-1792, www.mid-states1.com

Tow line and power-and-free conveyors: Webb-Stiles Co., 330-225-7761, www.webb-stiles.com

In-floor roller conveyor: Hytrol Conveyor Co., 870-935-3700, www.hytrol.com

Lift trucks: Yale Materials Handling, 252-758-9253, www.yale.com

Monorail, overhead cranes and manipulators: Knight Industries & Associates, 248-377-4950, www.knight-ind.com

Other overhead cranes: Unified Industries Inc., 517-546-3220, www.unified-ind.com; Uesco Industries, Inc., 708-385-7700, www.uescocranes.com

Articulated lift trucks: Landoll Corp., 800-428-5655, www.landoll.com

Tire handling system: Positech, 800-831-6026, www.positech-solutions.com

Robotic systems: ABB, 262-785-3400, www.abb.com

Doors and dock levelers: Rite-Hite Corp., 800-285-5956, www.ritehite.com

Containers: Buckhorn, Inc., 800-543-4454, www.buckhorninc.com

Email
Print
Reprint
Learn RSS

Talkback

We would love your feedback!

Post a comment

» VIEW ALL TALKBACK THREADS

Related Content

Sponsored Links


 
Advertisement
SPONSORED LINKS

More Content

  • Blogs
  • Webcasts

Blogs

  • Bob Trebilcock
    Company Briefings

    July 3, 2008
    NetSuite targets manufacturers
    The first time I was contacted by NetSuite, about five years ago, they had an intriguing story to tell about offering ERP functionality in an on-de......
    More
  • Frank
    On Your Worst Behavior

    July 1, 2008
    Wall-E is one of us
    Hollywood has done it again! Another big box office blockbuster features materials handling in several key scenes. Actually, you could say the star......
    More
  • View All BlogsRSS

Webcasts


Advertisements





MODERN MATERIALS HANDLING NEWSLETTERS

Click on a title below to learn more.

Resource Center E-Alert (Monthly)
Modern Early Edition (Monthly)
Modern Best Practices Update (Monthly)
Modern Product Showcase (Occasional)
MHPN Product Alert (Monthly)
MHPN Product Showcase (Occasional)
About Us   |   Contact Us   |   Advertising Info   |   Site Map   |   FREE Subscriptions   ||   RSS
© 2008 Reed Business Information, a division of Reed Elsevier Inc. All rights reserved.
Use of this Web site is subject to its Terms of Use | Privacy Policy
Please visit these other Reed Business sites